|
Cold Weather
Construction
Masonry construction can continue during both hot and cold weather
conditions. The ability to continue masonry construction in
adverse weather conditions requires consideration of how environmental
conditions may affect the quality of the finished masonry. In some
cases, environmental conditions may warrant the use of special
construction procedures to ensure that the masonry work is not adversely
affected.
Cold Weather Construction
Materials selected for normal temperature construction will
generally require little change during construction in low temperature
weather other than insure that their temperature is conducive to
hydration of the cement.
Mortar and Grout Performance
Hydration and strength development in mortar and grout generally occurs
at temperatures above 40° F (4.4° C) and only when sufficient
water is available. However, masonry construction may proceed when
ambient temperatures are below freezing, provided the mortar or grout
ingredients are heated and the temperature of the freshly constructed
masonry is maintained above freezing during the initial hours after
construction.
Effects of Freezing
The water content of mortar is a significant factor affecting mortar
properties. When mortars with water contents in excess of 8%
freeze, the resulting expansion has a disruptive effect on the
cement-aggregate matrix of the mortar (ref. 1). This disruptive
effect increases as the water content increases. Therefore, mortar
should not be allowed to freeze until the mortar water content is
reduced from the initial 11% to 16% range to a value below 6%. Dry
concrete masonry units have a demonstrated capacity to achieve this
moisture reduction in a relatively short time, commonly with
3 to 5 minutes (ref. 1).
Grout is a close relative of mortar in composition and performance
characteristics. During cold weather, however, special attention
must be directed toward the protection of grout because of the higher
water content and resulting disruptive expansion that can occur from
freezing of that water.
Like mortars, grouts undergo the hydration process, gain strength cool
down, lose moisture to the adjacent masonry units, and require
protection through material heating or enclosures. Unlike mortars,
grouts are confined within the enclosed cells of hollow concrete masonry
units. To maintain grout fluidity and mobility during placement,
water content must be maintained at a very high level. These
conditions make grouted masonry particularly vulnerable to detrimental
expansion with early freezing. Therefore, grouted masonry
needs to be protected for longer periods to allow the water content to
be dissipated.
Table 1a Cold Weather
Masonry Construction Requirements (ref. 1,3)
|
Ambient
Temperature |
Construction
Requirements |
|
25 to 40° F
(-3.9 to 4.4° C) or
masonry units below
40 F (4.4° C) |
Do not lay masonry
units having a temperature below 20° F (-6.7° C). Remove
visible ice on masonry units before the unit is laid in the
masonry. Heat mixing water or sand to produce mortar and
grout temperatures between 40 and 120° F (4.4 and 48.9°
C). Maintain mortar above freezing until placement. |
|
20 to 25° F
(-6.7 to -3.9° C) |
Same as above, plus use
heat sources on both sides of the masonry under construction and
install wind breaks when wind velocity exceeds 15 mph (24.1
km/hr). |
|
below 20° F (-6.7°
C) |
Same as above, plus
provide an enclosure for the masonry under construction and use
heat sources to maintain temperatures above 32° F (0° C) within
the enclosure. |
Table 1b Cold Weather
Masonry Protection Requirements (ref. 1,3)
|
Mean daily
temperature |
Protection
Requirements |
|
32 to 40° F
(0 to 4.4° C) |
Protect completed
masonry from rain or snow by covering with a weather-resistive
membrane for 24 hours after construction. |
|
25 to 32° F
(-3.9 to 0° C) |
Completely cover the
completed masonry with a weather-resistive membrane for 24 hours
after construction. |
|
20 to 25°F
(-6.7 to -3.9° C) |
Completely cover the
completed masonry with insulating blankets or equal protection for
24 hours after construction. |
|
below 20° F (-6.7°
C) |
Maintain masonry
temperature above 32° F (0°C) for 24 hours after construction by
enclosure with supplementary heat, by electric heating blankets,
by infrared heat lamps, or by other acceptable methods. |
Hot
Weather Construction
High
temperatures, solar radiation, and ambient relative humidity influence the
absorption characteristics of the masonry units and the setting time and
drying rate for mortar. When mortar gets too hot, it may lose water
so rapidly that the cement does not fully hydrate. Early surface
drying of the mortar results in decreased bond strength and less durable
mortar. Hot weather construction procedures involve keeping masonry
materials as cool as possible and preventing excessive loss from the
mortar. Specific hot weather requirements of the Specifications for
Masonry Structures (ref. 3) are shown in Tables 2a and 2b.
Table 2a -Hot Weather Masonry Preparation and Construction Requirements
(ref. 1,3)
|
Ambient temperature |
Preparation and
Construction requirements |
|
Above 100° F
(37.8°C) or above 90° F (32.2° C)
with a wind > 8 mph (12.9 km/hr) |
Maintain sand piles in a
damp, loose condition. Maintain temperature of mortar and grout
below120° F (48.9° C). Flush mixer, mortar transport
container, and mortar boards with cool water before they come into
contact with mortar ingredients or mortar. Maintain mortar consistency
by retempering with cool water. Use mortar within 2 hours of
initial mixing. |
|
Above 115° F
(46.1° C) or above 105° F (40.6° C) with a wind > 8mph (12.9
km/hr) |
Same as above, plus
materials and mixing equipment are to be shaded from direct
sunlight. Use cool mixing water for mortar and grout.
Ice is permitted in the mixing water as long as it is melted when
added to the other mortar or grout materials. |
Table 2b -Hot Weather Masonry
Protection Requirements (ref. 1,3)
|
Mean Daily
temperature |
Protection
Requirements |
| Above 100° F (37.8° C) or above 90° F (32.2° C)
with a wind > 8 mph (12.9 km/hr) |
Fog spray all newly
constructed masonry until damp, at least times a day until the
masonry is three days old. |
|